100 Axle Lines SPMTs Assist 3200t Giant Bridge Section Roll on the Barge-TrailerHome

                                                             From :  http://www.trailer-home.com/

With the strong support from TrailerHome's SPMT, Guangdong LIFT Engineering Machinery Co.,Ltd(GPEC) 
was contracted by Wuchang Shipbuilding Industry to transport 3200t giant bridge section roll-on barge for
Hong Kong-Zhuhai-Macau Bridge project in Zhongshan, Guangdong province.
  












This giant bridge section, which total weighed 3,200 tones and had the dimensions 132.6 m x 33.1 m, were 
transported from the fabrication facility yard to the barge by using total 100-axle lines SPMTs. So, how to move
 this giant steel structure onto the barge safely and accurately? As there's over 20m distance from the bridge 
section and barge, crane is not suitable for this project. Based on the analysis of actual situation, our client 
GPEC choose the better solution of Self Propelled Modular Trailer (SPMT), which is more cost
-effective and easier to operate.




















Detail SPMT transport system configuration: 
100 axle lines TJ-S2.43 SPMT (10 units - 6 lines module, 10 units - 4 lines module) compose 4 big SPMT modules
4 PPU (390kw Mercedes Benz engine for Power Pack Unit)
1 Wireless Remote control

 










Normally it will take 5-6 hours to roll-on, but in this project, we need complete the whole process in 2 hours as the
 reason of Tidal influence. Also, high precision is essential for roll-on, deviation is controlled smaller than 5mm in 
every 100m movement. This requires everyone and every steps close-cooperation and no mistake permitted. 
  
The most difficult is, when SPMT move onto the barge, the barge will swing and tilt with the change of weight. So how 
to keep it balance? Thanks to the hydraulic steady system of Tianjie SPMT, which adopt reliable German brand main 
components and have hydraulic compensation stroke of approx. 700mm (±350mm). Hydraulic support cylinder on
 suspension is connected to each other by steel pipes and hose. One cut-off valve (ball valve) is used for grouping the 
hydraulic cylinders. Support system is set to three hydraulic groups according to cargo weight, center of gravity location
 and road conditions. This ensures a uniform axle load on rough road while running. Besides, the barge is equipped 
with pressurized cabin to outward drainage to ensure the balance.



















Through two hours efforts, TrailerHome's SPMT successfully assist the 3200t giant bridge section roll-onto the barge,
 this isthe first step of HZMB CB02 project, one historic move in Chinese Bridge Construction area. But For Tianjie, this 
is just another case with SPMT.

More information please check http://www.trailer-home.com/
Or contact with us info@trailer-home.com we wil do our best effort to support you.

2015年10月25日星期日

TrailerHome SPMT modular trailer moves 420 ton cold box in Dalian,China

TrailerHome Heavy Industries’ close friend and client, Jinde, also known as Dalian Kingdom Logistics Group
 Co.Ltd. has moved one 420 tons cold box in Dalian on March 17, 2014. Wehas offered 48 axles lines SPMT
 modular trailers and a group of engineers to help Jinde to finish this project.


The cold box’s dimension is 67.25m×10m×10.6m and weighs 420 tons. THI’s SPMT engineer Mr. Wu Hui
 has suggested using 24axles each for 4 files combination to do the transportation. The combination cont
ains two 6 axles self-propelled11 module and one PPU 375.

Since the cold box is a cube shape, so it is easy to locate its center of gravity and load it on the 4 files SPMT.
 The vehicle supports the cold box with 4 points. After loading, the vehicle had a deformation of 30mm, simil
ar to the calculated values. No deformation happened in the joint part.


The transportation was happened inside the shipyard. First the SPMT turns 90 degrees in a limited area.
 Then move backward for about 500 meters to the right position. After arriving in the correct position, tech
nicians will adjust the height of the SPMT to keep the cold box in a horizontal level. Then adjust the cente
rline of the coldbox till it is parallelled to thegantry crane, accuracy ±5mm. Lift the cold box up and move it 
to the right place.


Executives from Dalian Kingdom Logistics and Linde Group transportation supervision company h both
 spoke highly of TrailerHome’s SPMT was incredibly stable and flexible. It is truly a great advantage to ha
ve Tianjie’s support as a client and friend.”said Jinde’s project manager.

For more information,
Please contact with us..
Contact : Mr . Peng
Tel :       +86 139 1828 5343
Email :  Info@trailer-home.com 
WEB: www.trailer-home.com